My name is Katie. I am a Kindergartener in Mrs. Cariker’s and Mrs. French’s class at St. John’s. When I was just a baby, Pastor Klinkenberg baptized me and, a year later, he baptized my best friend, my cousin, Caroline Kunau. We both wore the.... Continue reading…
Finish work is the focus on the interior of the Sanctuary. All of the fire sprinklers, new lighting, and finish painting have been completed. The scaffolding inside the building is being removed this week. Once removed, work will begin on restoration of the Continue reading…
We are over half way through the Sanctuary restoration and the new bathroom/locker rooms are close to completion. This week all exterior brick and mortar is now.... Continue reading…
scaffolding started going up on the interior - all of the old grout has been completely removed - bathroom/locker rooms is ahead of schedule and looking great Continue reading…
Both locker rooms and have been demoed fully. All old fixtures, tile, walls, and many past renovations of electrical and plumbing have been removed. The plumbers are prepping for new sewer lines by have the concrete floors cut open. Very soon we will see the new walls being installed and all... Continue reading…
Work on all phases of our project is moving along as planned. The renovation work in Walker Hall to add bathrooms and fire suppression begins.
Exterior
The task of installing the new structural fasteners continues on schedule. By the middle of June, all of the dry fixed anchors will be... Continue reading…